Westports Malaysia adds Mitsui cranes as Port Klang expansion scales up
Westports Malaysia takes delivery of Mitsui E&S RTGs and completes CT10 reclamation, moving to double Port Klang capacity to 28m TEU.
Westports Malaysia is scaling up its yard operations to meet immediate demand while clearing the first major construction hurdle in a project that will eventually double its annual handling capacity. The delivery of eight Mitsui E&S rubber-tyred gantry (RTG) cranes, with seven more due in December, coincides with the completion of reclamation works for Container Terminal 10 (CT10) at Port Klang.
Westports, the operator of the container terminal, confirmed the delivery of the first batch of Mitsui E&S cranes this week. Once the remaining units arrive next month, the operator will manage a fleet of 227 RTGs. These diesel-driven units provide a safe working load of 40.6 tonnes and can stack containers one-over-six. The equipment is intended to strengthen yard-handling capacity as the terminal responds to growing operational demand.
The equipment arrival follows the October completion of reclamation and ground-improvement works for CT10, the first phase of the Westports 2 expansion. This stage involved 4.6 million cubic metres of sand fill and 12.5 million linear metres of prefabricated vertical drains over a 24-month period. With the site prepared, work now shifts to the construction of the quay, container yard, and supporting infrastructure.
Mitsui E&S currently holds a 14.03% share of the RTG market, ranking third behind ZPMC at 40.15% and Konecranes at 15.9%, according to the WorldCargo News 2026 survey. The Westports 2 project, launched in September 2024, will eventually add eight berths on Pulau Indah, aiming to grow the terminal’s total annual capacity from 14 million TEU to 28 million TEU.
Why it matters
The expansion of the RTG fleet to 227 units signals that Westports is prioritizing yard fluidity to manage current volume spikes before the new berths come online. For shipowners and charterers, this investment in yard-handling capacity reduces the risk of shoreside bottlenecks that often plague expanding gateways during construction phases.
The choice of Mitsui E&S equipment provides a look at the terminal’s procurement strategy. While ZPMC dominates the global RTG market, Westports is leaning on the third-largest supplier to outfit its yard. This suggests a commitment to the specific 1-over-6 stacking configuration and diesel drive systems of the Japanese manufacturer as the terminal prepares for higher-density operations.
The completion of the CT10 reclamation moves the Westports 2 project from the preparation phase into active infrastructure building. Doubling capacity to 28 million TEU will shift the competitive balance in Southeast Asian transshipment, and the arrival of new hardware now confirms that the operator is increasing its operational tempo well ahead of the new berth openings.
What to watch
Watch for the commencement of quay construction at CT10 and the rollout of the remaining seven berths on Pulau Indah, which will determine how quickly Westports can translate its new yard capacity into actual berth productivity. The arrival of the final seven cranes in December will complete the current fleet expansion, providing the immediate capacity needed while the terminal begins the multi-year task of building out its 28 million TEU future.
Source: World Cargo News